July 23rd: Digging a trench across the road to connect the sewer line to our lot
July 26th: The beginning of excavating the house
August 6th: The forms are put in and ready for cement
August 7th: The next day the cement truck comes and begins to pour cement
August 10th: The cement walls are in for the basement
View from the back yard
Soon they will be bringing in the dirt to fill the front yard all in...about 6 feet of fill dirt